2026-2-25

Customer Pain Points

Phase I already installed 1 MWp of photovoltaic capacity, but without energy storage support.

The facility still needs to purchase hundreds of thousands of kWh from the grid each month, resulting in high electricity costs.

Further optimization of the energy structure is required to reduce dependence on the utility grid.
Customized Solution

PV Expansion: Phase II added 1.17 MWp of solar capacity, bringing the total installed capacity to 2.17 MWp.

Energy Storage Configuration: A containerized energy storage system with a capacity of 2,088 kWh, featuring high integration and rapid deployment.

Core Design: DC-coupling technology with complete physical isolation between the DC side and AC side to enhance system safety.

Operating Strategy: Solar power prioritized for self-consumption; surplus energy stored, with the grid serving only as a supplementary source.
Project Value

✅ Significantly reduces grid electricity purchases, directly lowering energy costs.
✅ Containerized design enables modular, fast deployment, ideal for efficient delivery in overseas projects.
✅ DC-coupling technology improves overall energy utilization efficiency.
✅ AC/DC isolation ensures safe and stable system operation.
✅ Effectively shortens the investment payback period.