1044kWh Solar-plus-Storage Project for a Large Cold Chain Warehouse in Cape Town, South Africa
An LVK 1044kWh C&I BESS with three 120kW MPPT controllers DC-coupled to a 1.2MW rooftop PV system, protecting Cape Town cold chain inventory from frequent national load-shedding blackouts.
Project Overview
Project Background
Customer Needs
South Africa is experiencing frequent, nationwide power rationing; sudden, hours-long blackouts occurring multiple times a day have become the norm. The facility stores high-value goods; if power outages cause the refrigeration units to shut down for extended periods, the entire inventory would be ruined. Relying solely on backup diesel generators entails prohibitively high fuel costs.
Application Focus
Backup Power
Solution Design
Integrated ESS Design For Site Operations

System Architecture
Coordinated Power Flow
1044 kWh BESS + 3x 120kW MPPT + 1.2 MW Rooftop PV (DC-coupled) + Anti-Load-Shedding EMS

Results & Benefits
Project Outcomes
Reduced the cold chain center's base electricity costs by 52%.
Eliminated approximately 7% in energy conversion losses typically associated with the PV-to-AC inverter followed by AC-to-DC rectification for charging process.
Successfully mitigated the risk of cold chain disruptions caused by frequent power outages in South Africa; the projected payback period (ROI) is 3.5 years.